Expansion of Hong Kong |
Construction Phase Quarterly EM&A Report No.20 (1 October to 31 December 2020) |
|
||||
Contents
3RS |
Three-Runway System |
AAHK |
Airport Authority Hong Kong |
AECOM |
AECOM Asia Company Limited |
AFCD |
Agriculture, Fisheries and Conservation Department |
AIS |
Automatic Information System |
ANI |
Encounter Rate of Number of Dolphins |
APM |
Automated People Mover |
AW |
Airport West |
BHS |
Baggage Handling System |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DEZ |
Dolphin Exclusion Zone |
DO |
Dissolved Oxygen |
EAR |
Ecological Acoustic Recorder |
EIA |
Environmental Impact Assessment |
EM&A |
Environmental Monitoring & Audit |
EMIS |
Environmental Mitigation Implementation Schedule |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ET |
Environmental Team |
FCZ |
Fish Culture Zone |
HKBCF |
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities |
HKIA |
Hong Kong International Airport |
HSF |
High Speed Ferry |
IEC |
Independent Environmental Checker |
LKC |
Lung Kwu Chau |
MTCC |
Marine Traffic Control Centre |
MMHK |
Mott MacDonald Hong Kong Limited |
MMWP |
Marine Mammal Watching Plan |
MSS |
Maritime Surveillance System |
MTRMP-CAV |
Updated Marine Travel Routes and Management Plan for Construction and Associated Vessel |
NEL |
Northeast Lantau |
NWL |
Northwest Lantau |
PAM |
Passive Acoustic Monitoring |
SC |
Sha Chau |
SCZ |
Speed Control Zone |
SCLKCMP |
Sha Chau and Lung Kwu Chau Marine Park |
SS |
Suspended Solids |
STG |
Encounter Rate of Number of Dolphin Sightings |
SWL |
Southwest Lantau |
The Manual |
The Updated EM&A Manual |
The Project |
The Expansion of Hong Kong International Airport into a Three-Runway System |
The SkyPier Plan |
Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier |
TSP |
Total Suspended Particulates |
WL |
West Lantau |
WMP |
Waste Management Plan |
Executive Summary
The “Expansion of Hong Kong International
Airport into a Three-Runway System” (the Project) serves to meet the future air
traffic demands at Hong Kong International Airport (HKIA). On 7 November 2014,
the Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014)
for the Project was approved and an Environmental Permit (EP) (Permit No.:
EP-489/2014) was issued for the construction and operation of the Project.
Airport Authority Hong Kong (AAHK) commissioned
Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental
Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A)
works during the construction phase of the Project in accordance with the
Updated EM&A Manual (the Manual).
This is the 20th Construction Phase
Quarterly EM&A Report for the Project which summarises the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 October 2020 to 31 December 2020.
Key Activities in the Reporting Period
EM&A Activities Conducted in the Reporting
Period
The EM&A programme was undertaken in
accordance with the Manual of the Project. Summary of the monitoring activities
during this reporting period is presented as below:
Monitoring Activities |
Number of Sessions |
1-hour Total Suspended Particulates (TSP) air quality monitoring |
96 |
Noise monitoring |
52 |
Water quality monitoring |
39 |
Vessel line-transect surveys for Chinese White Dolphin (CWD) monitoring |
6 |
Land-based theodolite tracking survey effort for CWD monitoring |
6 |
Environmental auditing works, including weekly
site inspections of construction works conducted by the ET and bi-weekly site
inspections conducted by the Independent Environmental Checker (IEC), audit of SkyPier High Speed Ferries (HSF), audit of construction and
associated vessels, and audit of implementation of Marine Mammal Watching Plan
(MMWP) and Dolphin Exclusion Zone (DEZ) Plan, were conducted in the reporting
period. Based on information including ET’s observations, records of Maritime
Surveillance System (MSS), and contractors’ site records, it is noted that
environmental pollution control and mitigation measures were properly
implemented and construction activities of the Project in the reporting period
did not introduce adverse impacts to the sensitive receivers.
Snapshots of Good Environmental
Practices in the Reporting Period
|
|
|
Installation of Energy Efficient Battery System |
Use of CIC carbon assessment tool to monitor carbon emissions of on-site construction process |
Obtained ISO 50001:2018 Energy Management System Certification |
Key examples of good site practices implemented
in the Project are highlighted as below:
1. Replacing traditional diesel generators with an
energy efficient battery system for tower crane operation to improve site
safety, minimize carbon emissions and noise levels.
2. A carbon assessment tool established by
Construction Industry Council (CIC) was deployed by a contractor to monitor
carbon emissions of on-site construction process. Aided by this software
application, contractor can measure the carbon footprint of their project and
analyse their carbon emissions data in an effective manner.
3. A 3RS contractor obtained ISO 50001:2018 Energy
Management System certification in Dececember 2020 to
improve the energy use and enhance the energy consumption performance during
the construction operation.
Summary Findings of the EM&A
Programme
The
monitoring works for construction dust, construction noise, water quality,
construction waste, landscape & visual, and CWD were conducted during the
reporting period in accordance with the Manual.
Monitoring
results of construction dust, construction noise, construction waste, and CWD
monitoring did not trigger the corresponding Action and Limit Levels in the
reporting period.
The water
quality monitoring results for all parameters, except suspended solids (SS) and
chromium, obtained during the reporting period were within the corresponding
Action and Limit Levels stipulated in the EM&A programme. Relevant
investigation and follow-up actions will be conducted according to the EM&A
programme if the corresponding Action and Limit Levels are triggered. For SS
and chromium, some testing results triggered the relevant Action or Limit
Level, and the corresponding investigations were conducted accordingly. The
investigation findings concluded that the case was not related to the Project.
To conclude, the construction activities in the reporting period did not
introduce adverse impact to all water quality sensitive receivers.
The key
findings of the EM&A programme during the reporting period is summarised as
below:
|
Yes |
No |
Details |
Analysis / Recommendation / Remedial Actions |
Breach of Limit Level^ |
|
√ |
No breach of Limit Level was recorded. |
Nil |
Breach of Action Level^ |
|
√ |
No breach of Action Level was recorded. |
Nil |
Complaints Received |
√ |
|
A complaint regarding solid waste and suspected open burning at 3RS was received on 6 Oct 2020 |
ET requested the relevant contractors for details related to the complaint. Site inspections and on-site investigation were also conducted by ET and IEC during which there was no related observation found on improper storage of solid waste or opening burning. All contractors were reminded to continue with the proper handling of general waste. The case was considered closed. |
A complaint regarding oil spillage from barges at 3RS project area was received on 15 Oct 2020. |
ET requested the relevant contractors for details related to the complaint. Regular site inspections and night-time ad-hoc inspections were also conducted by ET during which there was no observation indicating malpractice leading to oil spillage. All contractors were reminded to continue with their current proper practice in handling of oil and fuel to prevent spillage. The case was considered closed. |
|||
A complaint regarding illegal fuel delivery at 3RS project area was received on 20 Oct 2020. |
ET requested the relevant contractors for details related to the complaint. Regular site inspections and night-time ad-hoc inspections were also conducted by ET during which there was no observation indicating malpractice leading to fuel spillage. ET also conducted random check on contractors’ fuel purchasing record of Ultra Low Sulphur Diesel (ULSD) or equivalent were purchased by the contractors. All contractors were reminded to continue with their current proper practice in handling fuel and implementation on their spill response plans. The case was considered closed. |
|||
A complaint regarding dust issue at 3RS construction site area was received on 6 Nov 2020. |
ET requested the relevant contractor to provide information related to the complaint. During regular site inspections, no dust issue was recorded at the alleged area. The Contractor has reviewed and updated the dust control management plan to enhance water spraying to strengthen their dust suppression measure. All contractors were reminded to properly and adequately implement dust suppression measures especially in the current dry season to prevent air pollution on site. The case was considered closed. |
|||
A complaint regarding illegal refuel delivery leading to water pollution at 3RS project area was received on 19 Nov 2020. |
ET requested the relevant contractors to provide information related to the complaint. Regular site inspections and night-time ad-hoc inspections were also conducted by ET during which no occurrence regarding oil spillage onto sea surface was observed. ET also conducted a night-time inspection along the reclaimed land during which no oil spillage onto the sea surface from fuel transfer activities was observed. All contractors were reminded to continue with their current proper handling of oil and fuel on site and implementation on their spill response plans. The case was considered closed. |
|||
A complaint regarding illegal cement discharge and domestic waste disposal from marine vessel was received on 19 Nov 2020. |
ET requested the relevant contractor to provide information related to the complaint. ET conducted day-time and night-time inspections on the concerned vessel after receiving the complaint and checked the site inspection records of the vessel around the alleged period, and no adverse observation was made. The Contractor had followed their contract-specific Spill Response Plan and provided spill kits on the vessel. To follow up, the relevant contractor was reminded to strictly follow the standard operation procedures for cement refilling works and the contract-specific Spill Response Plan. The case was considered closed. |
|||
A complaint regarding smoke and dust from a contractor was received on 27 Nov 2020. |
ET requested the relevant contractors to provide information related to the complaint. During regular site inspections, dust generation from vehicular movements was observed in the alleged area on one occasion and was rectified by the Contractor afterwards. The Contractors implemented water spraying according to their dust control management plans. All contractors were reminded to properly and adequately implement dust suppression measures especially in the current dry season and to prevent air pollution on site. The case was considered closed. |
|||
Notification of any summons and status of prosecutions |
|
√ |
No notification of summons or prosecution were received. |
Nil |
Changes that affect the EM&A |
|
√ |
There was no change to the construction works that may affect the EM&A. |
Nil |
Remarks:
^Only
triggering of Action or Limit Level found related to Project works is counted
as Breach of Action or Limit Level.
On 7
November 2014, the Environmental Impact Assessment (EIA) Report (Register No.:
AEIAR-185/2014) for the “Expansion of Hong Kong International Airport into a
Three-Runway System” (the Project) was approved and an Environmental Permit
(EP) (Permit No.: EP-489/2014) was issued for the construction and operation of
the Project.
Airport Authority Hong Kong (AAHK) commissioned
Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental
Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A)
works during the construction phase of the Project in accordance with the
Updated EM&A Manual (the Manual) submitted under EP Condition 3.1[1].
AECOM Asia Company Limited (AECOM) was employed by AAHK as the Independent
Environmental Checker (IEC) for the Project.
The Project covers the expansion of the
existing airport into a three-runway system (3RS) with key project components
comprising land formation of about 650 ha and all associated facilities and
infrastructure including taxiways, aprons, aircraft stands, a passenger
concourse, an expanded Terminal 2, all related airside and landside works and
associated ancillary and supporting facilities. The submarine aviation fuel
pipelines and submarine power cables also require diversion as part of the
works.
Construction of the Project is to proceed in
the general order of diversion of the submarine aviation fuel pipelines,
diversion of the submarine power cables, land formation, and construction of
infrastructure, followed by construction of superstructures.
The updated overall phasing programme of all
construction works was presented in Appendix A of the Construction Phase
Monthly EM&A Report No. 7 and the contract information was presented in
Appendix A of the Construction Phase Monthly EM&A Report No. 58.
This is the 20th Construction Phase Quarterly EM&A Report
for the Project which summarises the key findings of the EM&A programme
during the reporting period from 1 October 2020 to 31 December 2020.
The Project’s organisation structure is
provided in Appendix
A. Contact details of the key personnel have been updated and provided
in Table 1.1.
Table
1.1: Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Project Manager’s Representative (Airport Authority Hong Kong) |
Principal Manager, Environmental Compliance, Sustainability |
Lawrence Tsui |
2183 2734 |
Environmental Team (ET) (Mott MacDonald Hong Kong Limited) |
Environmental Team Leader |
Terence Kong |
2828 5919 |
Deputy Environmental Team Leader |
Heidi Yu |
2828 5704 |
|
Deputy Environmental Team Leader |
Daniel Sum |
2585 8495 |
|
Independent Environmental Checker (IEC) (AECOM Asia Company Limited) |
Independent Environmental Checker |
Jackel Law |
3922 9376
|
Deputy Independent Environmental Checker |
Roy Man |
3922 9141
|
Reclamation Works:
Party |
Position |
Name |
Telephone |
Contract 3205 DCM (Package 5) (Bachy Soletanche - Sambo Joint Venture) |
Deputy Project Director |
Min Park |
9683 0765 |
Environmental Officer |
Steven Chan |
6288 0189 |
|
Contract 3206 Main Reclamation Works (ZHEC-CCCC-CDC Joint Venture) |
Project Manager |
Alan Mong |
3763 1352
|
Environmental Officer |
Kwai Fung Wong |
3763 1452 |
Airfield Works:
Party |
Position |
Name |
Telephone |
Contract 3301 North Runway Crossover Taxiway (FJT-CHEC-ZHEC Joint Venture) |
Deputy Project Director |
Kin Hang Chung |
9800 0048 |
Environmental Officer |
Joe Wong |
6182 0351 |
|
Contract 3302 Eastern Vehicular Tunnel Advance Works (China Road and Bridge Corporation) |
Project Manager |
Dickey Yau |
5699 4503 |
Environmental Officer |
Dennis Ho |
5645 0563 |
|
Contract 3303 Third Runway and Associated Works (SAPR Joint Venture) |
Project Manager |
Andrew Keung |
6277 6628 |
Environmental Officer |
Max Chin |
6447 5707 |
|
Contract 3307 Fire Training Facility (Paul Y. Construction Company Limited) |
Project Manager |
Steven Meredith |
6109 1813 |
Environmental Officer |
Albert Chan |
9700 1083 |
Third Runway Concourse:
Party |
Position |
Name |
Telephone |
Contract 3402 New Integrated Airport Centres Enabling Works (Wing Hing Construction Co., Ltd.) |
Contract Manager |
Michael Kan |
9206 0550 |
Environmental Officer |
Lisa He |
5374 3418 |
|
Contract 3403 New Integrated Airport Centres Building and Civil Works (Sun Fook Kong Construction Limited) |
Project Manager |
Alice Leung |
9220 3162 |
Environmental Officer |
Alpha Chia |
9626 1114 |
|
Contract 3405 Third Runway Concourse Foundation and Substructure Works (China Road and Bridge Corporation – Bachy Soletanche Group Limited – LT Sambo Co., Ltd. Joint Venture) |
Project Manager |
Francis Choi |
9423 3469 |
Environmental Officer |
Jacky Lai |
9028 8975 |
Terminal 2 (T2) Expansion:
Party |
Position |
Name |
Telephone |
Contract 3503 Terminal 2 Foundation and Substructure Works (Leighton – Chun Wo Joint Venture) |
Project Manager |
Eric Wu |
3973 1718 |
Environmental Officer |
Gomez Yuen |
9098 7807 |
|
Contract 3508 Terminal 2 Expansion Works (Gammon Engineering & Construction Company Limited) |
Project Director |
Richard Ellis |
6201 5637 |
Environmental Officer |
Gena Tsang |
9511 2283 |
Automated People Mover (APM) and
Baggage Handling System (BHS):
Party |
Position |
Name |
Telephone |
Contract 3601 New Automated People Mover System (TRC Line) (CRRC Puzhen Bombardier Transportation Systems Limited and CRRC Nanjing Puzhen Co., Ltd. Joint Venture) |
Project Manager |
Hongdan Wei |
158 6180 9450 |
Environmental Officer
|
Jasmine Tso
|
5968 6926 |
|
Contract 3602 Existing APM System Modification Works (Niigata Transys Co., Ltd.) |
Project Manager |
Kunihiro Tatecho |
9755 0351 |
Environmental Officer |
Yolanda Gao |
5399 3509 |
|
Contract 3603 3RS Baggage Handling System (VISH Consortium) |
Project Manager |
K C Ho |
9272 9626 |
Environmental Officer |
Eric Ha |
9215 3432 |
Construction Support
(Facilities):
Party |
Position |
Name |
Telephone |
Contract 3721 Construction Support Infrastructure Works (China State Construction Engineering (Hong Kong) Ltd.) |
Site Agent |
Thomas Lui |
9011 5340 |
Environmental Officer |
Xavier Lam |
9493 2944 |
|
Contract 3722 Western Support Area – Construction Support Facilities (Tapbo Construction Company Limited and Konwo Modular House Limited Joint Venture) |
Deputy Project Director |
Philip Kong |
9049 3161 |
Environmental Officer |
Sampson Lo |
9752 9118 |
Airport Support Infrastructure:
Party |
Position |
Name |
Telephone |
Contract 3801 APM and BHS Tunnels on Existing Airport Island (China State Construction Engineering (Hong Kong) Ltd.) |
Project Manager |
Tony Wong |
9642 8672 |
Environmental Officer |
Federick Wong |
9842 2703 |
|
Contract 3802 APM and BHS Tunnels and Related Works (Gammon Construction Limited) |
Project Director |
John Adams |
6111 6989 |
Environmental Officer |
Andy Leung |
9489 0035 |
Construction Support (Services / Licences):
Party |
Position |
Name |
Telephone |
Contract 3901A Concrete Batching Facility (K. Wah Concrete Company Limited) |
Project Manager |
Benedict Wong |
9553 2806 |
Environmental Officer |
C P Fung |
9874 2872 |
|
Contract 3901B Concrete Batching Facility (Gammon Construction Limited) |
Senior Project Manager |
Gabriel Chan |
2435 3260 |
Environmental Officer |
Rex Wong |
2695 6319 |
The contact information for
the Project is provided in Table 1.2. The public can contact us through
the following channels if they have any queries and comments on the
environmental monitoring data and project related information.
Table
1.2: Contact Information of the Project
Channels |
Contact Information |
Hotline |
3908 0354 |
|
|
Fax |
3747 6050 |
Postal Address |
Airport Authority Hong Kong HKIA Tower 1 Sky Plaza Road Hong Kong International Airport Lantau Hong Kong Attn: Environmental Team Leader Mr Terence Kong c/o Mr Lawrence Tsui (TRD) |
The key activities of the Project carried out
in the reporting period included reclamation works and land-based works. Works
in the reclamation areas included DCM works, marine filling, seawall and
facilities construction, together with runway and associated works such as
bored piling for approach lights. Land-based works on existing airport island
involved mainly airfield works, foundation and substructure work for Terminal 2
expansion, modification and tunnel work for APM and BHS systems, and
preparation work for utilities, with activities include site establishment,
site office construction, road and drainage works, cable ducting, demolition of
existing facilities, piling, and excavation works.
The locations of the key construction
activities are presented in Figure
1.1.
The status for all environmental aspects is
presented in Table 1.3. The EM&A requirements
remained unchanged during the reporting period.
Table
1.3: Summary of
Status for All Environmental Aspects under the Updated EM&A Manual
Parameters |
EM&A Requirements |
Status |
Air Quality |
|
|
Baseline Monitoring |
At least 14 consecutive days before commencement of construction work |
The baseline air quality monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
At least 3 times every 6 days |
On-going |
Noise |
|
|
Baseline Monitoring |
Daily for a period of at least two weeks prior to the commencement of construction works |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
Weekly |
On-going |
Water Quality |
|
|
General Baseline Water Quality Monitoring for reclamation, water jetting and field joint works |
Three days per week, at mid-flood and mid-ebb tides, for at least four weeks prior to the commencement of marine works. |
The baseline water quality monitoring result has been reported in Baseline Water Quality Monitoring Report and submitted to EPD under EP Condition 3.4. |
General Impact Water Quality Monitoring for reclamation, water jetting and field joint works |
Three days per week, at mid-flood and mid-ebb tides. |
On-going |
Initial Intensive Deep Cement Mixing (DCM) Water Quality Monitoring |
At least four weeks |
The Initial Intensive DCM Monitoring Report was submitted and approved by EPD in accordance with the Detailed Plan on DCM. |
Regular DCM Water Quality Monitoring |
Three times per week until completion of DCM works. |
On-going |
Sewerage and Sewage Treatment |
||
Methodology for carrying out annual sewage flow monitoring for concerned gravity sewer |
Methodology to be prepared and submitted to EPD at least one year before commencement of the operation of 3RS. |
To be prepared and submitted to EPD |
Details of the routine H2S monitoring system for the sewerage system of 3RS |
Details to be prepared and submitted to EPD at least one year before commencement of the operation of 3RS. |
To be prepared and submitted to EPD |
Waste Management |
|
|
Waste Monitoring |
At least weekly |
On-going |
Land Contamination |
|
|
Supplementary Contamination Assessment Plan (CAP) |
At least 3 months before commencement of any soil remediation works. |
The Supplementary CAP was submitted and approved by EPD pursuant to EP condition 2.20. |
Contamination Assessment Report (CAR) |
CAR to be submitted for golf course |
The CAR for Golf Course was submitted to EPD. |
CAR to be submitted for Terminal 2 Emergency Power Supply Systems
|
The CARs for Terminal 2 Emergency Power Supply System Nos.1 (Volumes 1 and 2), 2, 3, 4 and 5 were submitted to EPD. |
|
Terrestrial Ecology |
|
|
Pre-construction Egretry Survey Plan |
Once per month in the breeding season between April and July, prior to the commencement of HDD drilling works. |
The Egretry Survey Plan was submitted and approved by EPD under EP Condition 2.14. |
Ecological Monitoring |
Monthly monitoring during the HDD construction works period from August to March. |
The terrestrial ecological monitoring at Sheung Sha Chau was completed in January 2019. |
Marine Ecology |
|
|
Pre-Construction Phase Coral Dive Survey |
Prior to marine construction works |
The Coral Translocation Plan was submitted and approved by EPD under EP Condition 2.12. |
Coral Translocation |
- |
The coral translocation was completed on 5 January 2017. |
Post-translocation Monitoring |
As per an enhanced monitoring programme based on the Coral Translocation Plan |
The post-translocation monitoring programme according to the Coral Translocation Plan was completed in April 2018. |
Chinese White Dolphins (CWD) |
|
|
Baseline Monitoring |
6 months of baseline surveys before the commencement of land formation related construction works. Vessel line transect surveys: Two full surveys per month; Land-based theodolite tracking surveys: Two days per month at the Sha Chau station and two days per month at the Lung Kwu Chau station; and Passive Acoustic Monitoring (PAM): For the whole duration of baseline period. |
Baseline CWD results were reported in the CWD Baseline Monitoring Report and submitted to EPD in accordance with EP Condition 3.4. |
Impact Monitoring |
Vessel line transect surveys: Two full surveys per month; Land-based theodolite tracking surveys: One day per month at the Sha Chau station and one day per month at the Lung Kwu Chau station; and PAM: For the whole duration for land formation related construction works. |
On-going |
Landscape and Visual |
|
|
Landscape and Visual Plan |
At least 3 months before the commencement of construction works on the formed land of the Project. |
The Landscape & Visual Plan was submitted to EPD under EP Condition 2.18 |
Baseline Monitoring |
One-off survey within the Project site boundary prior to commencement of any construction works |
The baseline landscape & visual monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
Weekly |
On-going |
Environmental Auditing |
|
|
Regular site inspection |
Weekly |
On-going |
Marine Mammal Watching Plan (MMWP) implementation measures |
Monitor and check |
On-going |
Dolphin Exclusion Zone (DEZ) Plan implementation measures |
Monitor and check |
On-going |
SkyPier High Speed Ferries (HSF) implementation measures |
Monitor and check |
On-going |
Construction and Associated Vessels implementation measures |
Monitor and check |
On-going |
Complaint Hotline and Email Channel |
Construction phase |
On-going |
Environmental Log Book |
Construction phase |
On-going |
Taking into account the construction works in
the reporting period, impact monitoring of air quality, noise, water quality,
waste management, landscape & visual, and CWD were carried out in the
reporting period.
The EM&A programme also involved weekly
site inspections and related auditing conducted by ET for the checking of
implementation of required environmental mitigation measures recommended in the
approved EIA Report. To promote the environmental awareness and enhance the
environmental performance of the contractors, environmental trainings and
regular environmental management meetings were conducted during the reporting
period which are summarised as below:
● Four skipper trainings provided by ET;
● One dolphin observer training session provided
by ET;
● Two environmental briefings on EP and EM&A
requirements of the 3RS provided by ET; and
● Fifty-two environmental management meetings for
EM&A review with works contracts.
The EM&A programme has been following the
recommendations presented in the approved EIA Report and the Manual. A summary
of implementation status of the environmental mitigation measures for the
construction phase of the Project during the reporting period is provided in Appendix
B.
Impact 1-hour Total Suspended Particulates (TSP) monitoring was
conducted three times every six days at two representative monitoring stations
during the reporting period. The locations of monitoring stations are
described in Table 2.1 and presented in Figure
2.1.
The Action and Limit Levels of the air quality
monitoring stipulated in the EM&A programme for triggering the relevant
investigation and follow-up procedures under the programme are provided in Table 2.1 for reference.
Table 2.1: Impact Air Quality Monitoring
Stations
Monitoring Station |
Location |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AR1A |
Man Tung Road Park |
306 |
500 |
AR2 |
Village House at Tin Sum |
298 |
The air quality monitoring results
in the reporting period are summarised in Table 2.2 and the graphical
plot is presented in Appendix
C.
Table 2.2: Percentage of Air Quality
Monitoring Results within Action and Limit Levels
|
AR1A |
AR2 |
Oct 2020 |
100% |
100% |
Nov 2020 |
100% |
100% |
Dec 2020 |
100% |
100% |
Overall |
100% |
100% |
Note: The percentages are calculated by dividing the number of monitoring results within their corresponding Action and Limit Levels by the total number of monitoring results. |
All monitoring results were
within their corresponding Action and Limit Levels at all monitoring stations
in the reporting period.
General meteorological
conditions in the last month of the previous quarter and this reporting period
were recorded and summarised in Table 2.3.
Table 2.3: General Meteorological Condition
during Impact Air Quality Monitoring
|
Weather |
Dominant Wind Direction |
Sep 2020 |
Sunny to Cloudy |
Southwest |
Oct 2020 |
Sunny to Cloudy |
Northeast |
Nov 2020 |
Cloudy |
Northeast |
Dec 2020 |
Sunny to Cloudy |
Northeast |
No dust emission source was observed at the
monitoring stations during the monitoring sessions. As the sensitive receivers
were far away from the construction activities, with the implementation of dust
control measures, there was no adverse impact at the sensitive receivers
attributable to the works of the Project.
Impact noise monitoring was
conducted at four representative monitoring stations once per week during 0700
and 1900 in the reporting period. The locations of monitoring stations are
described in Table 2.4 and presented in Figure
2.1.
The Action and Limit Levels of the noise
monitoring stipulated in the EM&A programme for triggering the relevant
investigation and follow-up procedures under the programme are provided in Table 2.4 for reference.
Table 2.4: Impact Noise Monitoring Stations
Monitoring Station |
Location |
Action Level |
Limit Level |
NM1A |
Man Tung Road Park |
When one documented complaint is received from any one of the sensitive receivers |
75 dB(A) |
NM4 |
Ching Chung Hau Po Woon Primary School |
65dB(A) / 70 dB(A) (i) |
|
NM5 |
Village House in Tin Sum |
75 dB(A) |
|
NM6 |
House No. 1, Sha Lo Wan |
75 dB(A) |
|
Note: (i) The Limit Level for NM4 is reduced to 70dB(A) for being an educational institution. During school examination period, the Limit Level is further reduced to 65dB(A). |
The noise monitoring results in the reporting
period are summarised in Table 2.5 and the graphical plot is presented in Appendix
C.
Table 2.5: Percentage of Noise Monitoring
Results within Action and Limit Levels
|
NM1A |
NM4 |
NM5 |
NM6 |
Oct 2020 |
100% |
100% |
100% |
100% |
Nov 2020 |
100% |
100% |
100% |
100% |
Dec 2020 |
100% |
100% |
100% |
100% |
Overall |
100% |
100% |
100% |
100% |
Note: The percentages are calculated by dividing the number of monitoring results within their corresponding Action and Limit Levels by the total number of monitoring results. |
No complaints were received from any sensitive
receiver that triggered the Action Level. All monitoring results were also
within the corresponding Limit Levels at all monitoring stations in the
reporting period.
General meteorological conditions in the last month
of the previous quarter and this reporting period were recorded and summarised
in Table 2.6.
Table 2.6: General Meteorological Condition during
Impact Noise Monitoring
|
Weather |
Sep 2020 |
Sunny to Cloudy |
Oct 2020 |
Sunny to Cloudy |
Nov 2020 |
Cloudy |
Dec 2020 |
Sunny to Cloudy |
Major sources of noise dominating the
monitoring stations observed during the construction noise impact monitoring
were traffic noise near NM1A and aircraft noise near NM6. As the sensitive
receivers were far away from the construction activities, with the
implementation of noise control measures, there was no adverse impact at the
sensitive receivers attributable to the works of the Project.
During the reporting period, water quality
monitoring was conducted three days per week, at mid-flood and mid-ebb tides,
at a total of 23 water quality monitoring stations, comprising 12 impact (IM)
stations, 8 sensitive receiver (SR) stations, and 3 control (C) stations in the
vicinity of the water quality sensitive receivers around the existing airport
island in accordance with the Manual. The purpose of water quality monitoring
at the IM stations is to promptly capture any potential water quality impacts
from the Project before the impacts could become apparent at sensitive
receivers (represented by the SR stations). Table 2.7
describes the details of the monitoring stations. Figure
2.2 shows the locations of the monitoring stations.
Due to the completion of all marine-based DCM works
within December 2020, regular DCM monitoring was proposed to be ceased at all
monitoring stations starting within January 2021 and would be resumed if there
are marine-based DCM works in the coming future.
Table 2.7: Monitoring Locations and Parameters
for Impact Water Quality Monitoring
Description |
Coordinates Easting Northing |
Parameters |
||
|
|
|||
C1 |
Control Station |
804247 |
815620 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
DCM Parameters Total Alkalinity, Heavy Metals(2) |
C2 |
Control Station |
806945 |
825682 |
|
C3(3) |
Control Station |
817803 |
822109 |
|
IM1 |
Impact Station |
807132 |
817949 |
|
IM2 |
Impact Station |
806166 |
818163 |
|
IM3 |
Impact Station |
805594 |
818784 |
|
IM4 |
Impact Station |
804607 |
819725 |
|
IM5 |
Impact Station |
804867 |
820735 |
|
IM6 |
Impact Station |
805828 |
821060 |
|
IM7 |
Impact Station |
806835 |
821349 |
|
IM8 |
Impact Station |
808140 |
821830 |
|
IM9 |
Impact Station |
808811 |
822094 |
|
IM10 |
Impact Station |
809794 |
822385 |
|
IM11 |
Impact Station |
811460 |
822057 |
|
IM12 |
Impact Station |
812046 |
821459 |
|
SR1A(1) |
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) Seawater Intake for cooling |
812660
|
819977 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS |
SR2(3) |
Planned marine park / hard corals at The Brothers / Tai Mo To |
814166 |
821463 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
DCM Parameters Total Alkalinity, Heavy Metals(2)(4) |
SR3 |
Sha Chau and Lung Kwu Chau Marine Park / fishing and spawning grounds in North Lantau |
807571 |
822147 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
|
SR4A |
Sha Lo Wan |
807810 |
817189 |
|
SR5A |
San Tau Beach SSSI |
810696 |
816593 |
|
SR6A(5) |
Tai Ho Bay, Near Tai Ho Stream SSSI |
814739 |
817963 |
|
SR7 |
Ma Wan Fish Culture Zone (FCZ) |
823742 |
823636 |
|
SR8(6) |
Seawater Intake for cooling at Hong Kong International Airport (East) |
811623 |
820390 |
Notes:
(1)
With the operation of
HKBCF, water quality monitoring at SR1A station was commenced on 25 October
2018.
(2)
Details of
selection criteria for the two heavy metals for regular DCM monitoring refer to
the Detailed Plan on Deep Cement Mixing available on the dedicated 3RS website
(http://env.threerunwaysystem.com/en/ep-submissions.html). DCM specific water quality monitoring parameters
(total alkalinity and heavy metals) were only conducted at C1 to C3, SR2, and
IM1 to IM12.
(3) According
to the Baseline Water Quality Monitoring Report, C3 station is not adequately
representative as a control station of impact/ SR stations during the flood
tide. The control reference has been changed from C3 to SR2 from 1 September
2016 onwards.
(4) Total
alkalinity and heavy metals results are collected at SR2 as a control station
for regular DCM monitoring.
(5) As the
access to SR6 was obstructed by the construction activities and temporary
structures for Tung Chung New Town Extension, the monitoring location has been
relocated to SR6A starting from 8 August 2019.
(6) The
monitoring location for SR8 is subject to further changes due to silt curtain
arrangements and the progressive relocation of this seawater intake.
The Action and Limit Levels for general water
quality monitoring and regular DCM monitoring stipulated in the EM&A
programme for triggering the relevant investigation and follow-up procedures
under the programme are presented in Table 2.8. The
control and IM stations during flood tide and ebb tide for general water
quality monitoring and regular DCM monitoring are presented in Table 2.9.
Table 2.8: Action and Limit Levels for
General Water Quality Monitoring and Regular DCM Monitoring
Parameters |
Action Level |
Limit Level |
||
Action and Limit Levels for general water quality monitoring and regular DCM monitoring (excluding SR1A & SR8) |
||||
DO in mg/l (Surface, Middle & Bottom) |
Surface and Middle 4.5 mg/l |
Surface and Middle 4.1 mg/l 5 mg/l for Fish Culture Zone (SR7) only |
||
Bottom 3.4 mg/l |
Bottom 2.7 mg/l |
|||
SS in mg/l |
23 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
37 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
Turbidity in NTU |
22.6 |
36.1 |
||
Total Alkalinity in ppm |
95 |
99 |
||
Representative Heavy Metals for regular DCM monitoring (Chromium)(6) |
0.2 |
0.2 |
||
Representative Heavy Metals for regular DCM monitoring (Nickel) (6) |
3.2 |
|
3.6 |
|
Action and Limit Levels SR1A |
|
|
|
|
SS (mg/l) |
33 |
42 |
||
Action and Limit Levels SR8 |
|
|
|
|
SS (mg/l) |
52 |
|
60 |
|
Notes:
1. For DO measurement, Action or Limit
Level is triggered when monitoring result is lower than the limits.
2. For parameters other than DO, Action
or Limit Level of water quality results is triggered when monitoring results is
higher than the limits.
3. Depth-averaged results are used unless
specified otherwise.
4. Details of selection criteria for
the two heavy metals for regular DCM monitoring refer to the Detailed Plan on
Deep Cement Mixing available on the dedicated 3RS website http://env.threerunwaysystem.com/en/ep-submissions.html)
5. The Action and Limit Levels for the
two representative heavy metals chosen will be the same as that for the
intensive DCM monitoring.
6. Due
to the completion of all marine-based DCM works within December 2020, regular
DCM monitoring was proposed to be ceased at all monitoring stations starting
within January 2021 and would be resumed if there are marine-based DCM works in
the coming future.
Table
2.9: The Control
and Impact Stations during Flood Tide and Ebb Tide for General Water Quality
Monitoring and Regular DCM Monitoring
Control Station |
Impact Stations |
Flood Tide |
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
SR21 |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6A, SR8 |
Ebb Tide |
|
C1 |
SR4A, SR5A, SR6A |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
Note:
1. As per findings of Baseline Water Quality Monitoring
Report, the control reference has been changed from C3 to SR2 from 1 Sep 2016
onwards.
The summary or results within their
corresponding Action and Limit Levels in the reporting period are presented in Table 2.10. The weather and sea conditions in the last
month of the previous quarter and this reporting period were recorded and
summarised in Table 2.11.
Table 2.10: Percentage of Water Quality
Monitoring Results within Action and Limit Levels
|
General Water Quality Monitoring |
Regular DCM Monitoring |
|||||
DO (Surface and Middle) |
DO (Bottom) |
SS |
Turbidity |
Alkalinity |
Chromium |
Nickel |
|
Oct 2020 |
100% (437/437) |
100% (437/437) |
99.8% (486/487) |
100% (437/437) |
100% (300/300) |
100% (300/300) |
100% (300/300) |
Nov 2020 |
100% (420/420) |
100% (420/420) |
100% (468/468) |
100% (420/420) |
100% (288/288) |
100% (288/288) |
100% (288/288) |
Dec 2020 |
100% (490/490) |
100% (490/490) |
96.3% (526/546) |
100% (490/490) |
100% (336/336) |
99.7% (335/336) |
100% (336/336) |
Overall |
100% |
100% |
98.6% |
100% |
100% |
99.9% |
100% |
Note: The percentages are calculated by dividing the number of depth-averaged results complying with their corresponding Action and Limit Levels by the total number of depth-averaged results. |
Table 2.11: General Weather Condition and Sea
Condition during Impact Water Quality Monitoring
|
Weather |
Sea Condition |
Sep 2020 |
Sunny to Rainy |
Calm to Rough |
Oct 2020 |
Sunny to Cloudy |
Calm to Rough |
Nov 2020 |
Sunny to Cloudy |
Calm to Rough |
Dec 2020 |
Sunny to Cloudy |
Calm to Rough |
The monitoring results for all parameters,
except SS and chromium, obtained during the reporting period were within their
corresponding Action and Limit Levels stipulated in the EM&A programme.
Relevant investigation and follow-up actions will be conducted according to the
EM&A programme if the corresponding Action and Limit Levels are triggered.
For SS and chromium, some of the testing
results triggered the corresponding Action or Limit Levels in the reporting
period, and investigations were conducted accordingly. Summaries of results
triggering Action or Limit Level for SS and chromium are presented Table 2.12 to Table 2.14.
Details of the investigation findings were
presented in Construction Phase Monthly EM&A Report Nos. 58 and 60, which
concluded that all results triggering the Action or Limit Level were not
related to the Project.
Table 2.12: Summary of SS Compliance Status
(Mid-Ebb Tide)
IM1 |
IM2 |
IM3 |
IM4 |
IM5 |
IM6 |
IM7 |
IM8 |
IM9 |
IM10 |
IM11 |
IM12 |
SR1A |
SR2 |
SR3 |
SR4A |
SR5A |
SR6A |
SR7 |
SR8 |
|
15/12/2020 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17/12/2020 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
D |
|
|
19/12/2020 |
|
D |
D |
D |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
No. of result triggering Action or Limit Level |
0 |
1 |
1 |
1 |
2 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
Table 2.13: Summary of SS Compliance Status
(Mid-Flood Tide)
IM1 |
IM2 |
IM3 |
IM4 |
IM5 |
IM6 |
IM7 |
IM8 |
IM9 |
IM10 |
IM11 |
IM12 |
SR1A |
SR3 |
SR4A |
SR5A |
SR6A |
SR7 |
SR8 |
|
15/10/2020 |
|
|
|
|
D |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17/12/2020 |
|
|
|
|
|
|
|
|
|
D |
|
|
|
|
|
|
|
|
|
19/12/2020 |
|
|
|
|
D |
D |
|
|
D |
D |
|
|
|
|
|
|
|
|
|
No. of result triggering Action or Limit Level |
0 |
1 |
1 |
0 |
2 |
1 |
0 |
0 |
1 |
2 |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Table 2.14: Summary of Chromium Compliance Status
(Mid-Ebb Tide)
IM1 |
IM2 |
IM3 |
IM4 |
IM5 |
IM6 |
IM7 |
IM8 |
IM9 |
IM10 |
IM11 |
IM12 |
|
22/12/2020 |
|
|
|
|
|
|
|
|
|
|
|
|
No. of result triggering Action or Limit Level |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
Note: The monitoring results
compiled with their corresponding Action or Limit Levels are presented in Appendix
C.
Legend: |
|
|
Result within corresponding Action and Limit Levels |
|
Result triggered the Action Level at monitoring station located upstream of the Project based on dominant tidal flow |
D |
Result triggered the Action Level at monitoring station located downstream of the Project based on dominant tidal flow |
D |
Result triggered the Limit Level at monitoring station located downstream of the Project based on dominant tidal flow |
|
Upstream station with respect to the Project during the respective tide based on dominant tidal flow |
|
Downstream station with respect to the Project during the respective tide based on dominant tidal flow |
In the reporting period, it is noted that most
monitoring results were within their corresponding Action and Limit Levels,
while only a minor number of results triggered their corresponding Action or
Limit Level, and investigations were conducted accordingly. Based on the
findings presented in Construction Phase Monthly EM&A Report Nos. 58 and
60, all cases that triggered the corresponding Action or Limit Level were not
related to the Project. Hence, the Project did not introduce adverse impact to
all water quality sensitive receivers. All required actions under the Event and
Action Plan were followed.
Nevertheless, the non-project related triggers
were attended to and initiated corresponding action and measures. As part of
the EM&A programme, the construction methods and mitigation measures for
water quality will continue to be monitored and opportunities for further
enhancement will continue to be explored and implemented where possible, to
strive for better protection of water quality and the marine environment.
In the meantime, the contractors
were reminded to implement and maintain all mitigation measures during weekly
site inspections and regular environmental management meetings. These include
maintaining mitigation measures properly for reclamation works including DCM
works, marine filling, seawall construction, and bored piling for approach
lights as recommended in the Manual.
In accordance with the Manual, waste generated
from construction activities was audited once per week to determine if wastes
were being managed in accordance with the Waste Management Plan (WMP) prepared
for the Project, contract-specific WMP, and any statutory and contractual
requirements. All aspects of waste management including waste generation,
storage, transportation, and disposal were assessed during the audits.
The Action and Limit Levels of the construction
waste are provided in Table 2.15.
Table
2.15: Action and
Limit Levels for Construction Waste
Monitoring Stations |
Action Level |
Limit Level |
Construction Area |
When one valid documented complaint is received |
Non-compliance of the WMP, contract-specific WMPs, any statutory and contractual requirements |
Weekly monitoring of the Project construction
works was carried out by the ET in the reporting period to check and monitor
the implementation of proper waste management practices.
Recommendations made by the ET included
provision and maintenance of proper chemical waste storage area, as well as
handling, segregation, and regular disposal of general refuse. The contractors
had taken actions to implement the recommended measures. Waste management
audits were carried out by ET according to the requirement of the Waste
Management Plan, Updated EM&A Manual and the implementation schedule of the
waste management mitigation measures in Appendix
B.
Based on updated contractors’ information,
summary of construction waste generated in the reporting period is presented in
Table 2.16. Proactive measures have been undertaken
during the re-configuration of T2 building. The contractor has
established the recycling strategy for C&D materials with proper planning
and design to maximize recycling and reuse. Dedicated recyclers were
employed for different kinds of recyclable materials by the contractor, and ET
and IEC have carried out site visits to recyclers’ facilities to review
recycling process. Recycling materials before leaving the site are
weighted by a weight bridge and monitored by CCTV system. Dedicated areas for
sorting of materials are established on site. Recyclable materials such as
steel, reinforcement bar, structural steel, aluminium, copper, other metals and
glass are sorted on-site and transported off-site for recycling. ET and IEC
have carried out site audits regularly and reviewed the trip ticket
system.
Table 2.16: Construction Waste Statistics
|
C&D(1) Material Stockpiled for Reuse or Recycle (m3) |
C&D Material Reused in the Project (m3) |
C&D Material Reused in other Projects (m3) |
C&D Material Transferred to Public Fill(3) (m3) |
Chemical Waste (kg) |
Chemical Waste (l) |
General Refuse (tonne) |
Oct 2020(2) |
7,679 |
121,985 |
1,724 |
10,267 |
60 |
1,800 |
2,242 |
Nov 2020(2) |
7,611 |
100,368 |
31 |
30,995 |
1,297 |
3,600 |
1,545 |
Dec 2020(2) |
20,497 |
52,073 |
4,879 |
4,027 |
240 |
5,980 |
2,223 |
Total |
35,787 |
274,426 |
6,634 |
45,289 |
1,597 |
11,380 |
6,010 |
Notes: 1. C&D refers to Construction and Demolition. 2. Paper, metals and/or plastics were recycled in the reporting period. 3. C&D materials not suitable for reuse on-site, including asphalt waste and sediment slurry, were transferred to public fill during the reporting period. |
There were no complaints,
non-compliance of the WMP, contract-specific WMPs, statutory and contractual
requirements that triggered Action and Limit Levels in the reporting period.
Marine sediment is managed
according to the EIA Report, Updated EM&A Manual and Waste Management Plan
of the Project. The sampling process, storage conditions of the excavated
marine sediment, treatment process, final backfilling location as well as
associated records were inspected and checked by ET and verified by IEC to
ensure they were in compliance with the requirements as stipulated in the Waste
Management Plan.
Sampling works for marine sediment
generated from the reclaimed land area was on-going during the reporting
period. The details of the marine sediment sampling, treatment and backfilling
will be reported in the subsequent EM&A Reports upon completion.
CWD monitoring was conducted by
vessel line transect survey at a frequency of two full surveys per month,
supplemented by land-based theodolite tracking survey and PAM. The frequency of
the land-based theodolite tracking survey during the construction phase was one
day per month at both Sha Chau (SC) and Lung Kwu Chau
(LKC) stations, as stipulated in the Manual. The vessel survey transects
followed the transect lines proposed in the Manual and are consistent with those used
in the Agriculture, Fisheries and Conservation Department (AFCD) long-term CWD
monitoring programme. The transect locations of CWD monitoring by vessel line
transect survey conducted from October to December 2020 are shown in Figure
2.3, whilst the land-based theodolite tracking survey stations are
described in Table 2.17 and depicted in Figure
2.4. The location of the PAM device is shown in Figure
2.10.
Table 2.17: Land-based Theodolite Tracking Survey
Station Details
Stations |
Location |
Geographical Coordinates |
Station Height (m) |
Approximate Tracking Distance (km) |
D |
Sha Chau (SC) |
22° 20’ 43.5” N 113° 53’ 24.66” E |
45.66 |
2 |
E |
Lung Kwu Chau (LKC) |
22° 22’ 44.83” N 113° 53’ 0.2” E |
70.40 |
3 |
The Action Level and Limit Level for CWD
monitoring were formulated by an action response approach using the running
quarterly dolphin encounter rates (STG and ANI) derived from baseline
monitoring data, as presented in the CWD Baseline Monitoring Report. The
derived values of Action and Limit Levels for CWD monitoring are shown in Table 2.18.
Table 2.18: Derived Values of Action Level
and Limit Level for Chinese White Dolphin Monitoring
|
NEL, NWL, AW, WL and SWL as a Whole |
Action Level |
Running quarterly STG < 1.86 & ANI < 9.35 |
Limit Level |
Two consecutive running quarterly (3-month) STG < 1.86 & ANI < 9.35 |
Survey
Effort
During the October to December
2020 reporting period, a total of six sets of vessel line transect survey
covering all transects in Northeast Lantau (NEL), Northwest Lantau (NWL), Airport West (AW), West
Lantau (WL) and Southwest Lantau (SWL) survey areas were conducted at a
frequency of twice per month, in each survey area.
A total of around 1,350 km of
survey effort was collected from these surveys, with around 85.9% of the total
survey effort being conducted under favourable
weather condition (i.e. Beaufort Sea State 3 or below with favourable
visibility). Details of the survey effort data are presented in Appendix
C.
CWD
Sighting
From October to December 2020,
there were a total of 45 sightings of CWDs, with 137 dolphins sighted (Table 2.19).
Amongst these sightings, 43 sightings with 135 dolphins were recorded during
on-effort searches under favourable weather
condition.
When breaking down the sightings
by survey areas, 2 sightings with 2 dolphins were recorded in NWL, 2 sightings
with 4 dolphins were recorded on AW transects, 27 sightings with 88 dolphins
were recorded in WL, while 14 sightings with 43 dolphins were recorded in SWL
during the current reporting period. No CWD was sighted in NEL survey area.
Compared with the last quarter
(i.e. July to September 2020), the total number of CWD sightings slightly
increased by a few, but the total number of dolphins dropped by 22%. The drop
in terms of number of dolphins was mainly attributed by the decline of the
number of dolphins in WL by 29% during the reporting period.
Compared with the same quarter of
last year (i.e. October to December 2019), there is an increase in terms of
both the total number of CWD sightings and the total number of dolphins by 18%
and 25% respectively, contributed by the increase in sightings and dolphins in
WL and SWL survey areas. However, there is a significant decline in both the
number of sightings and the number of dolphins in NWL by 78% and 89%
respectively.
Table 2.19 below shows the comparison of the numbers of sightings
and dolphins amongst the current reporting period, last quarter, and the same
quarter of last year.
Table 2.19: Summary of Number of CWD Sightings and
Number of Dolphins for the Same Quarter Last Year, Previous Quarter, and
Current Reporting Period
|
Same Quarter of Last Year |
Previous Reporting Period |
Current Reporting Period |
|
October to December 2019 |
July to September 2020 |
October to December 2020 |
NEL |
0 (0) |
0 (0) |
0 (0) |
NWL |
9 (19) |
1 (2) |
2 (2) |
AW |
1 (7) |
0 (0) |
2 (4) |
WL |
21 (71) |
24 (124) |
27 (88) |
SWL |
7 (13) |
17 (50) |
14 (43) |
Total |
38 (110) |
42 (176) |
45 (137) |
Note: Values in ( ) represent number of dolphins
The distribution of CWD sightings recorded from October to December 2020 is illustrated in Figure 2.5. In NWL including AW transects, all the CWD sightings were recorded at the southwestern part of the survey area with two sightings located west to the existing Hong Kong International Airport, while another two sightings located between Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road and the north Lantau coast near Sham Wat Wan. In WL, CWD sightings scattered amongst the survey area with the majority clustered near Peaked Hill and Yi O. In SWL, most of the dolphin sightings were recorded in the waters around Fan Lau and some sightings were scattered around the Soko Islands. No CWD sightings were recorded in NEL survey area. Details of the sighting data are presented in Appendix C.
Figure 2.5: Sightings Distribution of Chinese White Dolphins from October to
December 2020
Remarks: (1) Please note that there
are 45 pink
circles on the map indicating the sighting locations of CWD. Some of them were
very close to each other and therefore appear overlapped on this sighting
distribution map. (2) Marine park excludes land area and the landward boundary
generally follows the high water mark along the coastline.
Encounter Rate
The dolphin encounter rates for
the number of on-effort dolphin sightings per 100 km survey effort (STG) and
for the total on-effort number of dolphins per 100 km survey effort (ANI) in the
whole survey area (i.e. NEL, NWL, AW, WL and SWL) for October, November and
December 2020 are summarised in Table 2.20.
In this reporting period, both
the running quarterly STG and ANI increased from October to December 2020. No Action Level for CWD
monitoring was triggered during the reporting period. For the monthly ANI,
however, there was a significant drop from 17.80 in October to 7.19 in December 2020.
Compared with the previous
reporting period (i.e. July to September 2020), the running quarterly STG remained
relatively steady while the running quarterly ANI became lower. While comparing
with the same quarter of last year (i.e. October to December 2019), both the
running quarterly STG and ANI increased, from 2.80 to 3.71 and from 8.18 to
11.64 respectively. Encounter rates for these periods are summarised
in Table
2.20 and graphical presentation is provided in Appendix
C.
Table 2.20: Summary of Monthly and Running
Quarterly STG and ANI of Chinese White Dolphin for the Same Quarter Last Year,
Previous Quarter, and Current Reporting Period
|
Same Quarter of Last Year |
Previous Reporting Period |
Current Reporting Period |
||||||
|
Oct 19 |
Nov 19 |
Dec 19 |
Jul 20 |
Aug 20 |
Sep 20 |
Oct 20 |
Nov 20 |
Dec 20 |
Monthly STG |
3.33 |
2.50 |
2.56 |
6.84 |
1.90 |
1.18 |
3.89 |
3.30 |
3.99 |
Monthly ANI |
12.00 |
5.46 |
6.98 |
28.62 |
7.59 |
4.48 |
17.80 |
10.37 |
7.19 |
Running Quarterly STG |
3.91 |
3.42 |
2.80 |
4.88 |
4.81 |
3.23 |
2.24 |
2.73 |
3.71 |
Running Quarterly ANI |
15.32 |
11.63 |
8.18 |
21.16 |
19.01 |
13.23 |
9.54 |
10.52 |
11.64 |
Note: For detailed calculations of
encounter rates STG and ANI for the current reporting period, please refer to
the Construction Phase Monthly EM&A Report Nos. 58, 59 and 60.
Group Size
Between October and December
2020, the group size of CWD sightings ranged from 1 to 15 dolphins. The average
group size of CWDs was 3.0 dolphins per group, which is smaller than that of
the last quarter (4.2 dolphins per group). The average group size of CWDs in
this reporting quarter is slightly larger than that of the same quarter of last
year (2.9 dolphins per group).
In this reporting quarter, the
number of CWD sightings with medium group size (i.e. 3-9 dolphins) was slightly
higher than that with small group size (i.e. 1-2 dolphins). There was only one
CWD sighting with large group size (i.e. 10 or more dolphins) recorded in this
reporting period.
The majority of the medium sized
dolphin groups were recorded over the entire WL survey area and also in SWL
near Fan Lau. All sightings recorded at the southwestern part of NWL survey
area and also around the Soko Islands in SWL were
small sized groups. The only CWD sighting with large group size was recorded at
Fan Lau in SWL survey area. Sighting locations of CWD groups with different
group sizes are depicted in Figure
2.6.
Figure 2.6:
Sighting Locations of Chinese White Dolphins with Different Group Sizes
Remarks: (1) Please note that there are 45 circles on the map
indicating the sighting locations of CWD. Some of them were very close to each
other and therefore appear overlapped on this sighting distribution map. (2)
Marine park excludes land area and the landward boundary generally follows the
high water mark along the coastline.
Activities and Association with Fishing Boats
From October to December 2020,
four sightings of CWDs were recorded with feeding activities. Amongst
these sightings, one was observed in association with operating gillnetter in
AW.
The number of sightings with
feeding recorded in the current reporting period is lower than that in the
previous reporting period (i.e. 10 sightings involved feeding activities
between July and September 2020). The number of CWD sightings with feeding
activities is the same as that in the same quarter of last year (i.e. 4
sightings between October and December 2019).
The sighting locations of CWDs
engaged in different behaviour during the current
reporting period are illustrated in Figure 2.7.
Figure 2.7: Sighting Locations of Chinese White
Dolphins Engaged in Different Behaviours
Remarks: Marine park excludes land area and the
landward boundary generally follows the high water mark along the coastline.
Mother-calf Pairs
From October to December 2020,
seven sightings of CWDs were recorded with the presence of mother-and-unspotted
calf or mother-and-unspotted juvenile pairs, which is fewer than that recorded
in the previous reporting quarter (i.e. 11 sightings between July and September
2020). The number is higher than that recorded in the same quarter of last year
(i.e. three sightings between October and December 2019). All these seven
sightings were recorded in WL.
The locations of CWD sightings
with the presence of mother-and-calf and/or mother-and-unspotted juvenile pairs
are shown in Figure 2.8.
Figure 2.8: Sighting Locations of Mother-calf Pairs
Remarks: (1)
Please note that there are seven circles on the map indicating the sighting
locations of Mother-Calf pair. (2) Marine park excludes land area and the
landward boundary generally follows the high water mark along the coastline.
Photo Identification
Between October and December 2020, a total
number of 45 different CWD individuals were identified altogether for 81 times.
Re-sighting information of CWD individuals provides an initial idea of their
range use and apparent connection between different areas of Lantau waters.
Amongst these 45 different CWD individuals, 21 animals (i.e. SLMM003, SLMM007,
SLMM010, SLMM012, SLMM014, SLMM023, SLMM025, SLMM035, SLMM037, SLMM049,
SLMM052, WLMM007, WLMM028, WLMM060, WLMM070, WLMM071, WLMM073, WLMM079,
WLMM114, WLMM147 and WLMM150) were sighted for more than once.
Ten individuals including SLMM003,
SLMM010, SLMM023, SLMM037, SLMM049, WLMM007, WLMM028, WLMM070, WLMM073 and
WLMM114 were re-sighted in different survey areas during this reporting period.
All cross-area movements were between WL and SWL survey areas except that by
SLMM010, the most frequently re-sighted individual in this reporting quarter
which has been encountered in NWL, WL and SWL survey areas altogether for six
times. The number of CWD individuals re-sighted more than once and the number
of CWD individuals showing cross-area movement in the current reporting period
are both lower than those of the previous reporting quarter from July to
September 2020 (25 and 11 individuals respectively).
A summary of photo identification works is presented
in Table
2.21. Representative photos of the 45 identified individuals and
figures depicting the sighting locations of the aforementioned 21 re-sighted
individuals recorded in this reporting period are presented Appendix
C.
Table 2.21: Summary of Photo Identification
Individual ID |
Date of sighting |
Sighting Group No. |
Area |
|
Individual |
Date of sighting |
Sighting Group No. |
Area |
SLMM002 |
21-Oct-20 |
4 |
SWL |
|
WLMM007 |
21-Oct-20 |
4 |
SWL |
SLMM003 |
27-Oct-20 |
9 |
WL |
|
|
27-Oct-20 |
6 |
WL |
|
06-Nov-20 |
3 |
WL |
|
|
06-Nov-20 |
5 |
WL |
|
09-Dec-20 |
7 |
SWL |
|
|
|
6 |
WL |
|
10-Dec-20 |
4 |
SWL |
|
WLMM008 |
21-Oct-20 |
4 |
SWL |
SLMM007 |
27-Oct-20 |
6 |
WL |
|
WLMM018 |
21-Oct-20 |
3 |
SWL |
|
16-Nov-20 |
4 |
WL |
|
WLMM028 |
27-Oct-20 |
7 |
WL |
SLMM010 |
21-Oct-20 |
4 |
SWL |
|
|
10-Dec-20 |
7 |
SWL |
|
27-Oct-20 |
7 |
WL |
|
WLMM029 |
10-Dec-20 |
7 |
SWL |
|
06-Nov-20 |
6 |
WL |
|
WLMM056 |
27-Oct-20 |
6 |
WL |
|
17-Nov-20 |
1 |
NWL |
|
WLMM060 |
27-Oct-20 |
1 |
WL |
|
19-Nov-20 |
2 |
SWL |
|
|
|
2 |
WL |
|
10-Dec-20 |
4 |
SWL |
|
WLMM063 |
16-Dec-20 |
1 |
AW |
SLMM012 |
21-Oct-20 |
4 |
SWL |
|
WLMM064 |
16-Dec-20 |
2 |
WL |
|
19-Nov-20 |
2 |
SWL |
|
WLMM065 |
19-Oct-20 |
1 |
WL |
SLMM014 |
21-Oct-20 |
4 |
SWL |
|
WLMM070 |
21-Oct-20 |
4 |
SWL |
|
10-Dec-20 |
5 |
SWL |
|
|
27-Oct-20 |
1 |
WL |
SLMM022 |
27-Oct-20 |
7 |
WL |
|
WLMM071 |
27-Oct-20 |
1 |
WL |
SLMM023 |
21-Oct-20 |
3 |
SWL |
|
|
|
2 |
WL |
|
|
4 |
SWL |
|
WLMM073 |
21-Oct-20 |
3 |
SWL |
|
16-Nov-20 |
3 |
WL |
|
|
|
4 |
SWL |
SLMM025 |
21-Oct-20 |
3 |
SWL |
|
|
16-Nov-20 |
5 |
WL |
|
|
4 |
SWL |
|
WLMM076 |
27-Oct-20 |
4 |
WL |
SLMM031 |
21-Oct-20 |
2 |
SWL |
|
WLMM079 |
27-Oct-20 |
9 |
WL |
SLMM035 |
09-Dec-20 |
1 |
SWL |
|
|
06-Nov-20 |
3 |
WL |
|
|
5 |
SWL |
|
|
16-Nov-20 |
3 |
WL |
SLMM037 |
16-Nov-20 |
6 |
WL |
|
WLMM080 |
16-Nov-20 |
1 |
AW |
|
19-Nov-20 |
2 |
SWL |
|
WLMM085 |
27-Oct-20 |
8 |
WL |
|
09-Dec-20 |
5 |
SWL |
|
WLMM107 |
06-Nov-20 |
1 |
WL |
|
|
7 |
SWL |
|
WLMM114 |
21-Oct-20 |
4 |
SWL |
SLMM049 |
27-Oct-20 |
6 |
WL |
|
|
06-Nov-20 |
3 |
WL |
|
19-Nov-20 |
2 |
SWL |
|
|
16-Nov-20 |
6 |
WL |
SLMM050 |
21-Oct-20 |
4 |
SWL |
|
WLMM131 |
27-Oct-20 |
4 |
WL |
SLMM052 |
27-Oct-20 |
6 |
WL |
|
WLMM135 |
06-Nov-20 |
1 |
WL |
|
16-Nov-20 |
3 |
WL |
|
WLMM147 |
27-Oct-20 |
9 |
WL |
SLMM059 |
21-Oct-20 |
4 |
SWL |
|
|
06-Nov-20 |
3 |
WL |
SLMM064 |
06-Nov-20 |
1 |
WL |
|
|
16-Nov-20 |
3 |
WL |
SLMM073 |
16-Nov-20 |
4 |
WL |
|
WLMM149 |
06-Nov-20 |
1 |
WL |
|
|
|
|
|
WLMM150 |
27-Oct-20 |
7 |
WL |
|
|
|
|
|
|
06-Nov-20 |
5 |
WL |
|
|
|
|
|
WLMM158 |
27-Oct-20 |
3 |
WL |
|
|
|
|
|
WLMM160 |
06-Nov-20 |
5 |
WL |
|
|
|
|
|
WLMM163 |
06-Nov-20 |
5 |
WL |
Survey Effort
Between October and December
2020, a total of six days of land-based theodolite tracking survey effort were
completed, including three days on Lung Kwu Chau and three
days on Sha Chau. In total, six CWD groups were tracked from the Lung Kwu Chau station while no CWD groups were tracked from the
Sha Chau station, with an overall 0.17 CWD groups sighted per survey hour.
Information on survey effort and
CWD groups sighted during land-based theodolite tracking surveys are presented
in Table
2.22. Details on the survey effort and CWD groups tracked are
presented in Appendix
C. The first sighting locations of CWD groups tracked between October
and December 2020 are shown in Figure 2.9.
Table 2.22: Summary of Survey Effort and CWD Group of
Land-based Theodolite Tracking Survey
Land-based Station |
# of Survey Sessions |
Survey Effort (hh:mm) |
# CWD Groups Sighted |
CWD Group Sighting per Survey Hour |
October 2020 |
||||
Lung Kwu Chau |
1 |
06:00 |
1 |
0.17 |
Sha Chau |
1 |
06:00 |
0 |
0 |
TOTAL |
2 |
12:00 |
1 |
0.08 |
November 2020 |
||||
Lung Kwu Chau |
1 |
06:00 |
2 |
0.33 |
Sha Chau |
1 |
06:00 |
0 |
0 |
TOTAL |
2 |
12:00 |
2 |
0.17 |
December 2020 |
||||
Lung Kwu Chau |
1 |
06:00 |
3 |
0.5 |
Sha Chau |
1 |
06:00 |
0 |
0 |
TOTAL |
2 |
12:00 |
3 |
0.25 |
OVERALL |
6 |
36:00 |
6 |
0.17 |
Figure 2.9:
Plots of First Sightings of All CWD Groups from Land-based Stations
Remark:
Marine park excludes land area and the landward boundary generally follows the
high water mark along the coastline.
An Ecological Acoustic Recorder (EAR) has been deployed and
positioned to the south of Sha Chau Island inside the SCLKCMP (Figure
2.10) with 20% duty cycle, while PAM data from the EAR intends to
supplement the detection of CWD presence in the south Sha Chau area that are
not recorded visually by the land-based theodolite tracking survey and to
coincide the theodolite data when there is sighting from the land-based station
at Sha Chau. In this reporting period, the EAR has been retrieved on 22 October
and 3 December 2020 for data collection and subsequently redeployed. The EAR
will be deployed for about 4 weeks and retrieved in early January 2021 for annual data analysis, and
replaced by F-POD/C-POD for deployment at the same monitoring location with
effective from January 2021. As the period of data collection and
analysis takes more than four months, PAM results could not be reported in
quarterly intervals but report for supplementing the annual CWD monitoring
analysis.
During the reporting period, silt
curtains were in place by the contractors for marine filling works (similar to
the previous reporting period), in which dolphin observers were deployed by
each contractor in accordance with the Marine Mammal Watching Plan (MMWP).
Teams of at least two dolphin observers were deployed at 3 to 7 dolphin
observation stations by the contractors for continuous monitoring of the DEZ by
all contractors for DCM works, seawall construction and bored piling for
approach lights in accordance with the DEZ Plan. Trainings for the proposed
dolphin observers on the implementation of MMWP and DEZ monitoring were provided
by the ET prior to the aforementioned works, with a cumulative total of 703
individuals being trained and the training records were kept by the ET. From
the contractors’ MMWP observation records and DEZ monitoring records, no
dolphin or other marine mammals were observed within or around the silt
curtains or the DEZ in this reporting period. The contractors’ records were
also audited by the ET during site inspection.
Audits of acoustic decoupling for construction
vessels were carried out during weekly site inspection and summarised in Section 2.6.
Summary of audits of SkyPier HSFs route diversion and
speed control and construction vessel management are presented in Section 2.7 and Section 2.8 respectively.
Site inspections of the construction
works were carried out on a weekly basis to monitor the implementation of
proper environmental pollution control and mitigation measures for the Project.
Bi-weekly site inspections were also conducted by the IEC. Besides, ad-hoc
site inspections were conducted by ET and IEC if environmental problems were
identified, or subsequent to receipt of an environmental complaint, or as part
of the investigation work. These site inspections provided a direct means to
reinforce the specified environmental protection requirements and pollution
control measures in construction sites.
During site inspections, environmental
situation, status of implementation of pollution control and mitigation
measures were observed. Environmental documents and site records, including
waste disposal record, maintenance record of environmental equipment, and
relevant environmental permit and licences, were also checked on-site. Observations
were recorded in the site inspection checklist and passed to the contractor
together with the appropriate recommended mitigation measures where necessary in order to advise contractors on
environmental improvement, awareness and on-site enhancement measures.
The observations were
made with reference to the following information during the site inspections:
· The EIA and EM&A requirements;
· Relevant environmental protection
laws, guidelines, and practice notes;
· The EP conditions and other
submissions under the EP;
· Monitoring results of EM&A
programme;
· Works progress and programme;
· Proposal of individual works;
· Contract specifications on
environmental protection; and
· Previous site inspection results.
Good site practices were implemented in the
project to enhance environmental performance. Key examples are highlighted as
below:
1. Replacing traditional diesel generators with an
energy efficient battery system for tower crane operation to improve site
safety, minimize carbon emissions and noise levels.
2. A carbon assessment tool established by
Construction Industry Council (CIC) was deployed by a contractor to monitor
carbon emissions of on-site construction process. Aided by this software
application, contractor can measure the carbon footprint of their project and
analyse their carbon emissions data in an effective manner.
3. A 3RS contractor obtained ISO 50001:2018 Energy
Management System certification in December 2020 to improve the energy use and
enhance the energy consumption performance during the construction
operation.
|
|
|
Installation of Energy Efficient Battery System |
Use of CIC carbon assessment tool to monitor carbon emissions of on-site construction process |
Obtained certification of ISO 50001:2018 Energy Management System Standard |
Besides, advice were given when
necessary to ensure the construction workforce were familiar with relevant
procedures, and to maintain good environmental performance on site. Regular
toolbox talks on environmental issues were organised for the construction
workforce by the contractors to ensure understanding and proper implementation
of environmental protection and pollution control mitigation measures.
Implementation of applicable landscape and
visual mitigation measures (reference to the environmental protection measures
CM1 – CM10 in Appendix
B) is monitored regularly in
accordance with the Manual. The implementation status of the environmental
protection measures is summarised in Table 2.23. For trees which were managed under the
Project during the reporting period, relevant measures have been implemented by
Contracts 3302, 3503, 3602 and 3801. Contracts 3508 and 3802 would begin to
undertake tree management measures subject to the handover of site area
(Contract 3508: Q2 2021 (tentative); Contract 3802: to be confirmed). Those
trees which were within the Project boundary yet to be taken care by existing
3RS Contractors during the reporting period were managed by AAHK. The
total number of retained trees, transplanted trees and to-be-transplanted trees
under the management of Project are summarized in Table
2.24.
The total number of retained trees
of the Project as of December 2020 was 118. Compared to 147 retained trees
reported in the previous reporting quarter, the change in number was due to the
following reasons:
·
2 nos. of
trees near Airport North Interchange and 1 no. of tree in Area 3801/13 were
damaged due to adverse weather from typhoon Mangkhut
in September 2018 and typhoon Higos in August 2020
respectively, and subsequently removed by the Contractor in Aug 2020 (-3 nos.);
·
Some of the
Contractor’s initial tree survey areas which recently confirmed not to be works
areas and therefore excluded from the Project. Trees located in those areas
were removed from the retained tree list under the Project (-27 nos.); and
·
ET and
Contractor’s recent on-site inspections confirmed that the status of 1 no. of
tree near the Airport North Interchange should be retained tree (+1 no.).
Table 2.25 lists the affected tree ID together with the reasons
for change of retained tree status of the Project.
A total of six trees under
Contractor 3503 (i.e. T812, T814, T815, T829, T830 and T831) were transplanted
during the reporting quarter. Therefore, the cumulative total number of
transplanted trees of the Project has been increased from 8 from previous
reporting quarter to 14. The summary of transplanted trees is shown in Table 2.26. Photos of the
transplanted trees are presented in Table 2.27 and the locations of newly transplanted
trees during the reporting period are presented in Figure 2.11.
Table 2.23: Landscape and Visual –
Construction Phase Audit Summary
Landscape and Visual Mitigation Measures during Construction Implementation Status |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
CM1- The construction area and contractor’s temporary works areas shall be minimised to avoid impacts on adjacent landscape. |
The implementation of mitigation measures were checked by ET during weekly site inspection and clarified by the Contractors during the monthly Environmental Management Meetings. Implementation of the measures CM5, CM6 and CM7 by Contractors was observed. |
3RS Project contracts |
CM2 – Reduction of construction period to practical minimum. |
||
CM3 – Phasing of the construction stage to reduce visual impacts during the construction phase. |
||
CM4 – Construction traffic (land and sea) including construction plants, construction vessels and barges shall be kept to a practical minimum. |
||
CM5 – Erection of decorative mesh screens or construction hoardings around works areas in visually unobtrusive colours. |
||
CM6 – Avoidance of excessive height and bulk of site buildings and structures |
||
CM7 – Control of night-time lighting by hooding all lights and through minimisation of night working periods |
||
CM8 – All existing trees shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas |
Tree Protection Specifications have been provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project.
The Contractors’ performance on the implementation of the trees maintenance and protection measures were observed and checked by the ET weekly during construction period. |
3302, 3503, 3602, 3801
3508, 3802 (To be implemented) |
CM9 – Trees unavoidably affected by the works shall be transplanted where practical. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, if applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme |
Tree Transplanting Specifications have been provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees will unavoidably be affected by the construction works.
The Contractors were required to submit Method Statements for tree transplanting prior to the transplanting works. Tree inspections were conducted by ET to check the tree transplanting works implemented by the Contractors on site.
The Contractors’ performance on the implementation of trees maintenance and protection measures on transplanted trees were observed and checked by the ET bi-monthly during the 12-month establishment period after the completion of each batch of transplanting works.
Long term management of the transplanted trees were currently monitored by ET annually. |
3503, 3801
3508, 3802 (To be implemented) |
CM 10 – Land formation works shall be followed with advanced hydroseeding around taxiways and runways as soon as practical |
To be implemented around taxiways and runways as soon as practicable. |
To be implemented |
Table 2.24: Summary of the Number of Retained,
Transplanted and To-be-transplanted Trees in the Reporting Period
Existing |
|
|
|
|
Contract |
Retain (nos.) |
Transplanted (nos.) |
To-be-transplanted (nos.) |
|
Establishment Period |
Maintenance Period |
|||
3302 |
9 |
0 |
0 |
0 |
3503 |
19 |
9 |
0 |
0 |
3602 |
2 |
0 |
0 |
0 |
3801 |
88 |
0 |
5 |
0 |
Sub-total |
118 |
9 |
5 |
0 |
Provisional |
|
|
|
|
Contract |
Retain (nos.) |
Transplanted (nos.) |
To-be-transplanted (nos.) |
|
3508(1) |
155 |
0 |
22 |
|
Sub-total |
155 |
0 |
22 |
|
Grand Total |
273 |
14 |
22 |
Note:
(1) Actual tree
number is subject to confirmation after initial tree survey is conducted by the
Contractor.
Table 2.25: Summary of the Tree Status Updated
in the Reporting Period
Tree ID(s) |
Contract
|
Previous Status (Sep 2020) |
Current Status (Dec 2020) |
Remarks |
Impact to Retain Tree Number |
CT1889, CT1890, CT1892, CT1893, CT1894, CT1895, CT1897, CT1898, CT1899, CT1900, CT1901, CT1902, CT1904, CT1905, CT1906, CT1907, CT1908, CT1909, CT1910, CT1911, CT1912, CT1913, CT1914, CT1917, CT1933, CT1934, CT1935 |
3801 |
Retain |
Not within Project’s contract works area |
27 nos. of trees were confirmed not located within Project’s contract works area. |
– 27 nos. |
CT1400, CT1466 |
3801 |
Retain |
Removed |
2 nos. trees were uprooted by typhoon Mangkhut in Sep 2018. As the health conditions were deteriorated and would cause adverse impacts to the retained trees in close vicinity, they were removed in late 2020.
|
– 2 nos.
|
CT1863 |
3801 |
Retain |
Removed |
1 no. tree was removed due to damage by typhoon Higos in Aug 2020. |
– 1 nos. |
CT1407 |
3801 |
Fell |
Retain |
The status of one tree was updated to retain during site inspection in Dec 2020. |
+ 1 nos. |
|
|
|
|
|
Total 118 nos. updated to Dec 2020 |
Table 2.26: Summary of the Transplanted Trees
Updated in the Reporting Period
Tree ID |
Transplant Date |
Management Stage |
Management Agency |
Remarks |
CT276 |
3 May 2018 |
Establishment period 4 May 2018 – May 2019 |
Contract 3801 |
NA |
Maintenance period Jun 2019 – May 2028 |
Southern Landside Petrol Filling Station |
|||
CT1253 |
4 May 2018 |
Establishment period 5 May 2018 – May 2019 |
Contract 3801 |
|
Maintenance period Jun 2019 – May 2028 |
Southern Landside Petrol Filling Station |
|||
T835 |
22 Jan 2020 |
Establishment period 23 Jan 2020 – Jan 2021 |
Contract 3503 |
NA
|
T836 |
13 Dec 2019 |
Establishment period 14 Dec 2020 – Jan 2021 |
Contract 3503 |
|
T838 |
22 Jan 2020 |
Establishment period 23 Jan 2020 – Jan 2021 |
Contract 3503 |
|
CT1194 |
4 May 2018 |
Establishment period 5 May 2018 – May 2019 |
Contract 3801 |
NA |
Maintenance period Jun 2019 – May 2028 |
Southern Landside Petrol Filling Station |
Uprooted and collapsed due to Typhoon Higos on 18 August 2020. Tree removal was conducted as recommended by tree specialist of the contractor of Southern Landside Petrol Filing Station. |
||
CT1794 |
3 May 2018 |
Establishment period 4 May 2018 – May 2019 |
Contract 3801 |
NA |
Maintenance period Jun 2019 – May 2028 |
AsiaWorld-Expo |
The tree within the land parcel was acquired by the government for construction of emergency hospital to handle COVID19 pandemic at AsiaWorld-Expo. The tree was felled in late 2020. |
||
CT1795 |
3 May 2018 |
Establishment period 4 May 2018 – May 2019 |
Contract 3801 |
NA |
Maintenance period Jun 2019 – May 2028 |
AsiaWorld-Expo |
The tree within the land parcel was acquired by the government for construction of emergency hospital to handle COVID19 pandemic at AsiaWorld-Expo. The tree was felled in late 2020. |
||
Newly Transplanted Trees during the Reporting Period |
||||
T812 |
21 Dec 2020 |
Establishment period 22 Dec 2020 – Dec 2021 |
Contract 3503 |
Original Location: Airport South Interchange
Recipient Site: Chun Wan Road Interchange (Scenic Road) |
T814 |
20 Dec 2020 |
Establishment period 21 Dec 2020 – Dec 2021 |
Contract 3503 |
Original Location: Airport South Interchange
Recipient Site: Chek Lap Kok South Road (Scenic Road) Interchange |
T815 |
15 Dec 2020 |
Establishment period 16 Dec 2020 – Dec 2021 |
Contract 3503 |
Original Location: Airport South Interchange
Recipient Site: Chun Wan Road Interchange (Scenic Road) |
T829 |
18 Dec 2020 |
Establishment period 19 Dec 2020 – Dec 2021 |
Contract 3503 |
|
T830 |
14 Dec 2020 |
Establishment period 15 Dec 2020 – Dec 2021 |
Contract 3503 |
Original Location: Airport South Interchange
Recipient Site: Chun Yue Road Interchange |
T831 |
19 Dec 2020 |
Establishment period 20 Dec 2020 – Dec 2021 |
Contract 3503 |
Original Location: Airport South Interchange
Recipient Site: Chun Wan Road Interchange (Scenic Road) |
Table 2.27: Photos of the Existing
Transplanted Trees in the Reporting Period
Under 12-month Establishment Period: |
||
|
|
|
T835 |
T836 |
T838 |
Newly Transplanted Trees during the Reporting Period |
||
|
|
|
T812 |
T814 |
T815 |
|
|
|
T829 |
T830 |
T831 |
Under 10-year Long-term Management: |
|
|
|
CT276 |
CT1253 |
The Supplementary CAP was submitted
to EPD pursuant to EP Condition 2.20. The CARs for Golf Course and T2 Emergency
Power Supply System Nos.1 (Volumes 1 and 2), 2, 3, and 5 and No. 4 were
submitted to EPD in accordance with EP Condition 1.9 and the Supplementary CAP
in which no land contamination issues were identified. EPD has issued no
further comment for all the CARs and required ET to submit additional photos
for sides and bottom of some of sampling points after the removal of pipelines
to reaffirm no leakage from the pipelines concerned. Afterwards, the potential
land contamination concern of two concerned systems will be closed.
A summary of implementation status
of the environmental mitigation measures for the construction phase of the
Project during the reporting period is provided in Appendix
B.
The Marine Travel Routes and
Management Plan for High Speed Ferries of SkyPier
(the SkyPier Plan) was submitted to the Advisory
Council on the Environment for comment and subsequently submitted to and
approved by EPD in November 2015 under EP Condition 2.10. The approved SkyPier Plan is available on the dedicated website of the
Project. In the SkyPier Plan, AAHK has committed to
implement the mitigation measure of requiring HSFs of SkyPier
travelling between HKIA and Zhuhai / Macau to start diverting the route with
associated speed control across the area, i.e. Speed Control Zone (SCZ), with
high CWD abundance. The route diversion and speed restriction at the SCZ have
been implemented since 28 December 2015.
Due to the COVID-19 pandemic, all SkyPier HSF services have been suspended from 25 March 2020
until further notice. Two special ferry movements between HKIA SkyPier and Macau were arranged by the ferry operator and
were audited in the reporting period. The summary of the SkyPier
Plan monitoring result is presented in Graph
1. Besides, limited HSF services
from other destination were also provided starting from 28 October 2020.
The daily movements of
all SkyPier HSFs, including those not using the
diverted route, in the reporting period ranged between 0 and 3, which fell
within the maximum daily cap number of 125.
The average speeds of
all HSFs travelling through the Speed Control Zone (SCZ) ranged from 10.8 to
11.0 knots. All HSFs travelled through the SCZ with average speed within 15
knots in compliance with the SkyPier Plan.
Graph 1: Summary of SkyPier
High Speed Ferries Monitoring Results
In addition, the dolphin habitat
index was reviewed based on AFCD latest marine mammals monitoring report
findings and historical dolphin density records, and the grids for dolphin
hotspot remain unchanged. AAHK will continue to implement the SkyPier HSF route diversion and speed restriction according
to the approved SkyPier Plan.
On the implementation of the updated Marine Travel Routes and Management
Plan for Construction and Associated Vessels (MTRMP-CAV), the Maritime Surveillance System (MSS) automatically recorded deviation
cases such as speeding, entering no entry zone, and not traveling through the
designated gates. ET conducted bi-weekly audit of
relevant information including AIS data, vessel tracks and other relevant
records to ensure sufficient information were provided by the system and the
contractors complied with the requirements of the MTRMP-CAV. The contactors
submitted 3-month rolling vessel plans for construction vessel activities to
AAHK in order to help maintain the number of construction vessels to a
practicable minimum. The IEC also performed audit on the compliance of the
requirements as part of the EM&A programme.
During the reporting
period, deviations including speeding within the works area, entry from
non-designated gates, and entering no-entry zones were identified. After
investigation by the contractor’s Marine Traffic Control Centre (MTCC) representatives,
all the concerned captains were reminded to comply with the requirements of the
MTRMP-CAV.
A total of 4 skipper training workshops were
held by ET during the reporting period and 16
concerned captains of construction vessels associated with the 3RS contracts
were trained to familiarise them with the
predefined routes, general education on local cetaceans, guidelines for
avoiding adverse water quality impact, the required environmental practices /
measures while operating construction and associated vessels under the Project,
and guidelines for operating vessels safely in the presence of CWDs. Another 10
skipper training workshops were held with 18 captains by contractors’
Environmental Officers and competency tests were conducted subsequently with
the trained captains by ET.
With reference to Appendix E of the Manual, it
is noted that the key assumptions adopted in approved EIA report for the
construction phase are still valid and no major changes are involved. The
environmental mitigation measures recommended in the approved EIA Report remain
applicable and shall be implemented in undertaking construction works for the
Project.
During the reporting period, environmental
related licenses and permits required for the construction activities were
checked. No non-compliance with environmental statutory requirements was
recorded.
Seven
environmental complaints were received in the reporting period. All environmental
complaints were attended to and investigation was conducted by the ET in
accordance with the Manual and the Complaint Management Plan. The summary of
the complaints and analysis is presented in Table 3.1.
Table 3.1: Summary of Environmental
Complaints
Date of Complaint Received |
Details |
Analysis/ Remedial Actions |
Status |
6 Oct 2020 |
A complaint was received regarding solid waste and suspected open burning at the project area |
Investigation was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. The ET identified the potential related 3RS contractors and requested them for information regarding the complaint. Based on information provided by the contractors, no open burning was conducted within their respective construction sites. Besides, general waste was observed properly handled on site and toilets were cleaned by the workers regularly. Before formally receiving the complaint on 6 October 2020, IEC had conducted an ad-hoc site inspection in the alleged area on 30 September 2020. ET had also conducted an on-site investigation with IEC and contractor representatives on 5 October 2020. In both inspections, no opening burning, white smoke, or poor hygiene caused by storage of solid waste on site was observed. The security guards at the western pier and Environmental Officers from the potential related contractors all reported no white smoke was observed at the alleged area on 30 September 2020. Furthermore, the ET checked the construction vessels of all potential related contractors and confirmed no open burning or maintenance works were carried out on the construction vessels on 30 September 2020. Nevertheless, the ET reminded all contractors to continue with the proper handling of general waste produced from the construction site including collection and disposal. ET and IEC would continue to check contractors’ records on the proper handling of waste collection and disposal. |
Closed |
15 Oct 2020 |
A complaint was received regarding oil spillage from barges at 3RS project area |
Investigation was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. ET investigated the related work contractors of 3RS Project on the reclaimed land. Based on information provided by the contractors, no oil spillage incident from bunkering barge was recorded in September and early October 2020. During regular site inspections and night-time ad-hoc inspections conducted by ET in September and early October, no occurrence regarding oil spillage onto sea surface was observed. It was also observed that oil and fuel containers were properly stored at designated storage area and drip trays were provided. Besides, it was noted that the water quality monitoring results of the Project from 1 September 2020 to 10 October 2020 were within the corresponding Action and Limit Levels at all monitoring stations. Nevertheless, the ET will continue to remind all contractors to continue with their current proper practice in handling of oil and fuel to prevent spillage. |
Closed |
20 Oct 2020 |
A complaint was received regarding illegal fuel delivery leading to water pollution, air pollution and impact to CWDs at 3RS project area |
Investigation was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. The complainant mentioned that a barge pumping high sulphur diesel to oil drum and fuel tanker on the reclaimed land of 3RS construction site, which may cause air pollution. The complainant also mentioned that fuel spillage onto the sea surface was observed, which may cause impact to CWD. No further details of the case including date, time, location and name of barge could be provided. ET investigated the related work contractors of the Project on the reclaimed land and requested them for information regarding the case. Based on information provided by the contractors, no fuel spillage incident from bunkering barge was recorded in September and early October 2020. During the regular site inspections and night-time ad-hoc inspections conducted by ET in September and early October, no occurrence regarding fuel spillage onto sea surface was observed. It was also observed that oil and fuel containers were properly stored at designated storage area and drip trays were provided on site. No environmental malpractice leading to fuel spillage was observed. It was noted that 3RS water quality monitoring results from 1 September 2020 to 10 October 2020 were within the corresponding Action and Limit Levels at all monitoring stations. Moreover, the ET conducted random check on the fuel purchasing records of the related work contracts and all of them had purchased Ultra Low Sulphur Diesel (ULSD) or equivalent like EURO V. Nevertheless, the ET will continue to remind all contractors to continue with their current proper practice in handling fuel and implementation on their respective contract-specific spill response plans, including conducting regular spill drills and trainings. ET and IEC would continue to monitor 3RS water quality, air quality including the checking of contractors’ ULSD purchasing records and CWD monitoring results. |
Closed |
6 Nov 2020 |
A complaint was received regarding dust issue at 3RS construction site area |
Investigation was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. The ET identified the related 3RS contractor and requested the Contractor to provide more information regarding the complaint. According to the information provided by the Contractor, ground improvement works and filling material transferring activities were carried out at the alleged area. The watering of vehicular accesses following the circuits as set out in the contractor’s dust control management plan had been arranged. Based on ET’s regular site inspections, no dust issue was recorded at the alleged area. During the joint ad-hoc inspection of ET and IEC in the morning of 4 November 2020, dust emission from the vehicular movements was observed and the Contractor was advised to provide dust suppression mitigation measures to prevent fugitive dust generation. The Contractor also updated the dust control management plan to expand the water spray coverage at the alleged area. ET further conducted on-site investigations and observed that the exposed reclaimed land area and construction materials at the alleged area were in dry conditions. ET reminded the Contractor again to strictly follow the relevant requirements to prevent fugitive dust generation. The Contractor followed up to provide water spraying at the alleged area according to updated dust control management plan. It was noted that 3RS water quality monitoring results from 1 October 2020 to 8 November 2020 were within the corresponding Action and Limit Levels at all monitoring stations, except one case of SS triggered the corresponding Action Level at IM5 on 15 October 2020. Based on the investigation on the exceedance, the case was considered not due to the Project. Nevertheless, ET reminded the Contractor to strengthen their dust suppression measures and requested the Contractor to strengthen their dust suppression measures, proactively and timely review their management plan for dust control. ET will continue to remind all contractors to properly and adequately implement dust suppression measures especially in the current dry season and to prevent air pollution on site. |
Closed |
19 Nov 2020 |
A complaint regarding illegal refuel delivery leading to water pollution at 3RS project area was received on 19 Nov 2020. |
Investigation was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. No detail of the case such as location and name of the barge was provided in the complaint. ET investigated the related work contractors of 3RS Project on the reclaimed land. Based on the information provided by the contractors, no oil spillage incident from fuel transfer activities was recorded in October and up to early November 2020. During regular environmental site inspections and night-time ad-hoc inspections conducted by ET in October and early November 2020, no occurrence regarding oil spillage onto sea surface was observed. In addition, a night-time inspection along the reclaimed land in particular the western pier and north eastern pier was conducted on 24 November 2020 during which no oil spillage onto the sea surface from fuel transfer activities was observed. Regarding the reporting of oil and/or fuel spillage incident for the period from October and up to early November 2020, the ET did not receive any such reporting from the related work contractors. It was noted that 3RS water quality monitoring results from 1 October 2020 to 6 November 2020 were within the corresponding Action and Limit Levels at all monitoring stations, except one case of SS triggered the corresponding Action Level at IM5 on 15 October 2020. Based on the investigation on the exceedance, the case was considered not due to the Project. Nevertheless, the ET will continue to remind all contractors to properly handle oil and fuel on site and implement their respective contract-specific spill response plan including the conducting of regular spill drills and trainings, and to provide sufficient spill kits on site. ET and IEC would continue to monitor 3RS water quality. |
Closed |
19 Nov 2020 |
A complaint was received regarding illegal cement discharge and domestic waste disposal from a marine vessel |
Investigated was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. The ET identified the related 3RS contractor and requested the Contractor to provide more information regarding the complaint. According to the information provided by the Contractor, the identified marine vessel was responsible for cement mixing works and providing cement slurry for land improvement work during the alleged period from 29 to 31 August 2020. Although the Contractor had stopped operations on-board the vessel, ET conducted a night-time inspection on 23 November 2020 and day-time inspection on 24 November 2020. During both inspections, it was observed that the tops of the cement silo tanks were covered and the cement pipes were closed with metal plates with no discharge of cement effluent. Moreover, in ET’s inspections on the vessel on 18 August 2020 and 8 September 2020, it was observed that the set up on the vessel was properly in place and there was no environmental malpractice relating to the silo tank maintenance work as well as the handling of domestic waste. It was also noted that the Contractor had followed their contract-specific Spill Response Plan and provided spill kits on the vessel. No spill incident was reported by the Contractor during the alleged period. The environmental monitoring results for water quality, air quality and CWD monitoring in August 2020 were checked, where all the results were within the corresponding Action and Limit Levels except six cases of DO exceedances on 15 and 22 August 2020. Based on the investigation on the exceedances, the cases were considered not due to the Project. Following up on the complaint case, ET and IEC checked and noted the Contractor had executed corrective actions including conducting maintenance checking and inspections of vessels, provision of additional training for frontline staff, conducting an environmental emergency drill, and reviewing the implementation of their standard operating procedures in handling cement wastewater during maintenance works. The Contractor was also advised to implement suitable measures on issues regarding cement refilling works, spill response procedures and spill incident handling, and regular operation and maintenance. The ET would continue to remind all contractors to strictly follow both the standard operation procedures for cement refilling works and the contract-specific Spill Response Plan. ET and IEC would also conduct on-board inspections to ensure all similar cement mixing barges are maintaining good housekeeping and continue to monitor the Project’s water quality, air quality, and CWD monitoring results. |
Closed |
27 Nov 2020 |
A complaint was received regarding smoke and dust issue at 3RS project area |
Investigated was conducted by ET in accordance with the Manual and the Complaint Management Plan of the Project. The ET identified the related 3RS contractors and requested the Contractors to provide more information regarding the complaint. According to the information provided by the Contractors, marine filling works and unloading of construction materials at an aggregate mixing plant were carried out at the alleged area during the alleged period. Water spraying by water truck and water hose as set out in the Contractors’ dust control management plan were implemented at nearby haul road and stockpiling area. Sprinklers were also installed and operated at the stockpiling area of the aggregate mixing plant as dust suppression measure to further prevent fugitive dust. Based on ET’s regular site inspections, water spraying were implemented at the alleged area according to the Contractors’ dust control management plans. Around the alleged period, ET conducted regular site inspections in the alleged area on 3 and 17 November 2020, where on 3 November 2020 no smoke and dust emissions were observed at the alleged area. Dust generation from the vehicular movements was observed during the regular site inspection on 17 November 2020 and the related contractor was advised to implement sufficient dust suppression measures to keep haul roads in a damp condition. The Contractor subsequently rectified the issue by implementing water spraying on the concerned haul road. To follow up, ET reminded the related Contractors to continue implementing and strengthening their environmental mitigation measures for dust suppression measures. ET also reminded all contractors to properly and adequately implement dust suppression measures especially in the current dry season and to prevent air pollution on site. ET and IEC would continue to monitor the related contractors’ environmental mitigation measures for dust suppression during the environmental site inspections. |
Closed |
No
notification of summons nor prosecution was received during the reporting
period.
Cumulative statistics on valid exceedance,
non-compliance, complaints, notifications of summons and status of prosecutions
are summarised in Table 3.2
and Table 3.3.
Table 3.2: Statistics for Valid Exceedances
for the Environmental Monitoring
|
|
Total No. Recorded in the Reporting Period |
Total No. Recorded since the Project Commenced |
1-hr TSP |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Noise |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Waste |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Water |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
CWD |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Remark: Non-project
related triggers of Action or Limit Level are not shown in this table.
Table 3.3: Statistics for Non-compliance,
Complaints, Notifications of Summons and Prosecution
Reporting Period |
Cumulative Statistics |
|||
|
Non-compliance |
Complaints |
Notifications of Summons |
Prosecutions |
This reporting period |
0 |
7 |
0 |
0 |
From 28 December 2015 to end of the reporting period |
0 |
27 |
1 |
1 |
In this quarterly period from 1 October 2020 to
31 December 2020, the EM&A programme has been implemented as planned,
including 96 sets of air quality measurements, 52 sets of construction noise
measurements, 39 sets of water quality measurements, 6 complete sets of vessel
line transect surveys and 6 days of land-based theodolite tracking survey
effort for CWD monitoring, as well as environmental site inspections and waste
monitoring for the Project’s construction works.
The key activities
of the Project carried out in the reporting period included reclamation works
and land-based works. Works in the reclamation areas included DCM works, marine
filling, seawall and facilities construction, together with runway and
associated works such as bored piling for approach lights. Land-based works on
existing airport island involved mainly airfield works, foundation and
substructure work for Terminal 2 expansion, modification and tunnel work for
APM and BHS, and preparation work for utilities, with activities include site
establishment, site office construction, road and drainage works, cable
ducting, demolition, piling, and excavation works.
Monitoring
results of construction dust, construction noise, construction waste, and CWD
did not trigger the corresponding Action and Limit Levels in the reporting
period. All site observations made by the ET were recorded in the site
inspection checklists and passed to the contractor together with the
recommended follow-up actions.
For water quality, the water quality monitoring
results for all parameters, except SS and chromium, obtained during the
reporting period were within the corresponding Action and Limit Levels
stipulated in the EM&A programme. Relevant investigation and follow-up
actions will be conducted according to the EM&A programme if the
corresponding Action and Limit Levels are triggered. For SS and chromium, some
testing results triggered the relevant Action or Limit Levels, and the
corresponding investigations were conducted accordingly. The investigation
findings concluded that the cases were not related to the Project. In summary,
the construction activities in the reporting period did not introduce adverse
impact to all water quality sensitive receivers.
In total, two ferry
movements between HKIA SkyPier and Macau were audited
in the reporting period. All HSFs travelled through the SCZ with average speed
within 15 knots in compliance with the SkyPier Plan.
During the reporting period, ET
conducted bi-weekly audit of the MSS to ensure the system recorded all deviation cases
accurately and the contractors fully complied with
the requirements of the MTRMP-CAV. 4
skipper training workshops were held by ET and 10 skipper training workshops
were held by contractors’ Environmental Officers during the reporting period
and competency tests were conducted subsequently with the trained skippers by
ET.
On the implementation of MMWP,
dolphin observers were deployed by the contractors for laying of silt curtains
for marine filling works in accordance with the plan. On the implementation of
DEZ Plan, dolphin observers were deployed for continuous monitoring of the DEZ
by the contractors for DCM works, seawall construction and bored piling
for approach lights in
accordance with the DEZ Plan. Trainings for the proposed dolphin observers were
provided by the ET prior to the aforementioned works. From the
contractors’ MMWP observation records and DEZ monitoring records, no dolphin or
other marine mammals were observed within or around the silt curtains or the
DEZ in this reporting period. Audits of acoustic decoupling for construction
vessels were also carried out by the ET.
The recommended environmental mitigation
measures, as included in the EM&A programme, were effectively implemented
during the reporting period. Also, the EM&A programme implemented by the ET
has effectively monitored the construction activities and ensured the proper
implementation of mitigation measures.
[1] The Manual is available on the
Project’s dedicated website (accessible at:
http://env.threerunwaysystem.com/en/index.html)